Metal Container Corporation

Stark Building Expansion

The first phase of the Stark Building Expansion consisted of miscellaneous interior renovations to the existing facility, a 1,050 SF building expansion to the existing storage and receiving room area, a new 140,000 SF pre-engineered insulated metal building addition for the future bottle line equipment and new exterior infrastructure improvements including paving and underground utilities.

The second phase involved installation, steel erection, piping, electrical, and instrumentation of the process area and support area equipment to produce bottle cans.

S. M. Wilson & Co.